    Kitchen Remodeling in Broomall, PA

    In a Broomall split-level, the kitchen often sits half a level from the family room behind a bearing wall. Opening that wall changes how the whole house works, and it needs the right beam. We handle the drawings, the local permits and the build, and price your project at a free on-site walkthrough.

    Build your estimate

    Kitchen remodels for Broomall homes

    Broomall is full of 1950s–1960s ranches and split-levels with low ceilings and shallow original footings.

    • Kitchen and dining opened with flush or dropped beams, engineered for split-level framing.
    • Electrical service upgraded for modern appliances.

    What affects projects in Broomall

    • Split-level framing often needs new beams and footings before walls come out.
    • Sloped yards behind many Broomall homes make walkout additions and raised decks practical.

    Marple Township split-levels and colonials

    Broomall's housing is largely mid-century split-levels and 1970s colonials on generous lots. Those lots are the opportunity: there is usually room for a rear family-room addition, a garage conversion, or a full outdoor living build without fighting the setback line.

    Permits & local rules in Broomall

    Plans are reviewed by the Marple Township code office. We file and track every permit for you.

    1. Step 1. Zoning review: setbacks, lot coverage and height limits set by Broomall's local zoning rules.
    2. Step 2. Building permit filed with the township or borough code office serving Broomall (Pennsylvania Uniform Construction Code), using our in-house drawings.
    3. Step 3. Electrical and plumbing permits for new circuits, gas lines or relocated sinks.
    4. Step 4. Range-hood venting and makeup-air rules for larger hoods.
    5. Step 5. Rough and final inspections.

    Exact requirements depend on your property. We confirm them with the local office at your walkthrough.

    How your kitchen remodel gets built

    Every step, start to finish, handled by one design-build crew.

    1. 1Week 1

      In-home measure

      We measure the space, talk through how you cook and your budget.

    2. 2Weeks 2–3

      Layout & drawings

      In-house layout, cabinet plan, and any wall or beam engineering.

    3. 3Weeks 3–8

      Permits & ordering

      Township permits filed; cabinets and long-lead items ordered before demo.

    4. 4Weeks 8–10

      Demo & rough-in

      Tear-out, then plumbing, electrical, and lighting moved where needed.

    5. 5Weeks 10–13

      Cabinets & counters

      Cabinet install, then counters templated and set.

    6. 6Weeks 13–14

      Tile, trim & walkthrough

      Backsplash, fixtures, appliances, final inspection.

    Build your kitchen remodel estimate in Broomall

    Your project scope and material selections help us prepare for your free on-site walkthrough.

    Project size

    Cabinetry

    Countertops

    Flooring

    Add-ons · choose any

    FAQ

    Kitchen remodels in Broomall: common questions

    Call Free estimate